701 Butchery & Smokehouse, Weekly Update
Another big week of progress at 701 Butchery & Smokehouse!
This week we successfully set all of our trusses and custom-built gable ends. It was a big job that required bringing in a crane, but everything went up exactly like we wanted. We also got the roof completely sheeted and the gutter boards installed, so the building is really starting to take shape.
Behind the scenes, we met with our electrician and laid out the game plan for the next phase of electrical work. We also officially called in our metal, doors, and windows, so we're getting closer and closer to having this building dried in.
Every week it looks a little less like a construction site and a little more like the future home of 701 Butchery & Smokehouse.
Thank you again to everyone following along and supporting us as we build this thing from the ground up right here in Osage County!